City of Laramie SPT Phase 1 SCH 1 (Completed)

City of Laramie, SPT Phase 1 SCH 1

Special Purpose Tax projects for the City of Laramie are focused toward the rehabilitation of city streets and infrastructure. Phase 1 Schedule 1 included over 7 city blocks in 3 different locations. Through partnership with Simon Contractors, Stonehouse completed the demolition, storm water and surface earthwork portion of the 5 month project.

Earthwork- 24,500 CY
Surfacing Demolition- 41,000 SF
Subgrade Stabilization- 23,000 SY
Surface Restoration- 23,000 SY
Landscaping- 38,000 SF

Bookmark the permalink.